The selected CTP projects will be added to the STIP in Amendment 1 to the 2020-2023 STIP. Projects are scheduled for design in 2020-22, with construction scheduled for after 2023. Construction phases will be programmed for funding in accordance with individual project schedules and funds availability, with funds not expected to be available before 2023.
All projects that were submitted by communities for consideration were required to include cost sharing. At a minimum, community sponsors provided the required minimum federal match. Communities that committed additional funds were awarded more points in the scoring process. Projects were selected from community nominations ranked by a Project Evaluation Board, the total federal funding available is $56 million.
Selected projects are:
Region | Project Name | PEB Score | Criteria Set |
---|---|---|---|
CR | Seldon Road Extension Phase II | 152.1 | Urban/Rural |
CR | Akakeek, Ptarmiagan, and DeLapp Street - Heavy Use Road Improvements | 147.7 | Remote |
CR | Hemmer Road Upgrade Extension North to Bogard Road | 140.3 | Urban/Rural |
NR | Fort Yukon Road Improvements and ROW Safety | 138.8 | Remote |
CR | Redoubt Avenue and Smith Way Rehabilitation | 135.5 | Urban/Rural |
NR | Cordova Second Street Upgrades | 131.8 | Remote |
CR | South Trunk Road (Nelson Road) Improvements | 128.8 | Urban/Rural |
NR | Kiana Community-Wide Drainage Improvements | 128.7 | Remote |
NR | Healy Spur Road | 124.2 | Urban/Rural |
NR | Nome Front Street Resurfacing and Rehabilitation | 124 | Remote |
NR | Ruby Slough Road Phase II Final Design and Construction | 120.8 | Remote |
SR | Kodiak Otmeloi Way Reconstruction | 119.8 | Urban/Rural |
CR | Hermon Road Upgrade and Extension | 118.7 | Urban/Rural |
There are two sets of criteria for this project nomination opportunity: 1) Urban and Rural, and 2) Remote. Communities not connected to the road system by road or ferry are considered Remote. All other communities are considered Urban and Rural.
Please direct any questions to your regional planner. They will be your main point of contact during the CTP project nomination and evaluation process.
Timeline
Call for projects |
February 2019 |
Project submittal due |
September 15, 2019 |
DOT&PF regional review and |
October 2019 |
DOT&PF statewide PEB |
January 8th and 9th, 2020 |
Announce project awards |
March 2020 |
Initiate project agreement between DOT&PF and sponsoring agency |
Upon PEB approval and |