![]()
Below are timelines for project development:
| Project Development Timeline | |
| Task | Target Completion Date |
| Ground Survey | December 2017 |
| Geotechnical Investigation Report | Spring 2020 |
| ALP Approved by FAA | June 2020 |
| Environmental Assessment | April 2021 |
| Airport Final Design | April 2021 |
| Right-of-Way Acquisition | May 2021 |
| Advertise Project | September 2021 |
| Construction | 2021 / 2022 |
| Public Involvement Schedule - 2019 | |
| Task | Target Completion Date |
| Agency Notice | Commenting ended March 22 |
| Public Notice | Commenting ended April 21 |
| Agency Scoping Meeting (Anchorage) | March 6, 2019 |
| Public Meeting (Port Lions) | April 16, 2019 |
| Public Hearing on Final EA Draft (Port Lions) | Fall 2020 (date tbd) |
| Field Work Schedule 2018-2019 | |
| Task | Target Completion Date |
| Geotech Phase I Data Collection | March 2018 (done) |
| Fish Habitat Assessment | May 2018 (done) |
| Hazardous Materials Assessment | July 19, 2018 (done) |
| Wetland Delineation and Invasive Plant Species Survey | July 18-24, 2018 (done) |
| Cultural Resources Investigation | September 27, 2018 (done) |
| Geotechnical Phase 2 and Phase 3 Studies | Summer 2019 |
All dates may change as we move forward
![]()