Below are timelines for project development:
Project Development Timeline | |
Task | Target Completion Date |
Ground Survey | December 2017 |
Geotechnical Investigation Report | Spring 2020 |
ALP Approved by FAA | June 2020 |
Environmental Assessment | April 2021 |
Airport Final Design | April 2021 |
Right-of-Way Acquisition | May 2021 |
Advertise Project | September 2021 |
Construction | 2021 / 2022 |
Public Involvement Schedule - 2019 | |
Task | Target Completion Date |
Agency Notice | Commenting ended March 22 |
Public Notice | Commenting ended April 21 |
Agency Scoping Meeting (Anchorage) | March 6, 2019 |
Public Meeting (Port Lions) | April 16, 2019 |
Public Hearing on Final EA Draft (Port Lions) | Fall 2020 (date tbd) |
Field Work Schedule 2018-2019 | |
Task | Target Completion Date |
Geotech Phase I Data Collection | March 2018 (done) |
Fish Habitat Assessment | May 2018 (done) |
Hazardous Materials Assessment | July 19, 2018 (done) |
Wetland Delineation and Invasive Plant Species Survey | July 18-24, 2018 (done) |
Cultural Resources Investigation | September 27, 2018 (done) |
Geotechnical Phase 2 and Phase 3 Studies | Summer 2019 |
All dates may change as we move forward