Skip to content

Tentative Advertising Schedule

As of 05/21/2022 07:56 PM AKDT

This report includes projects that we anticipate advertising in the next 12 months. Unless otherwise stated, plans and specifications are not available at this time. Please check out the Bid Calendar for projects currently advertising.

Click here to generate an Excel file of the report below.

A STREET, NORTHERN LIGHTS TO 40TH AVE PAVEMENT PRESERVATION
Federal# / IRIS Program#: 0527030 / CFHWY00223
Region: Central Region
Location: Anchorage
Manager: Kevin L Jackson     Phone: (907)269-0610
Anticipate Advertising In: May 2022
Description of Work: Pavement preservation of A Street from Northern Lights Blvd to 40th Ave including improvements to drainage, intersections, ADA, roadside hardware, and utilities.
Engineer's Estimate Range: Between $2,500,000 and $5,000,000
Additional Info:

Boney Courthouse Mechanical Upgrades and Earthquake Repairs - Rebid
Federal# / IRIS Program#: N/A / 2501000113-A
Region: Central Region
Location: Anchorage
Manager: Eric F Hershey     Phone: (907)269-5572
Anticipate Advertising In: May 2022
Description of Work: This federally funded project includes replacement and upgrades to the existing mechanical heating, ventilating, and air conditioning (HVAC) equipment damaged during the 2018 earthquake. This includes replacing two central air handlers, return fans, louvres, heat exchangers, pumps, and associated ductwork in the penthouse mechanical room. The work also includes an Enhancement option to replace variable air volume boxes and upgrade associated controls in the basement.
Engineer's Estimate Range: Between $2,500,000 and $5,000,000
Additional Info:

Boney Courthouse Plaza Earthquake Repair
Federal# / IRIS Program#: PA-10-AK-4413-PW-00281 / 25RC091612
Region: Central Region
Location: Anchorage
Manager: Eric F Hershey     Phone: (907)269-5572
Anticipate Advertising In: May 2022
Description of Work: This federally reimbursable contract includes the replacement of concrete sidewalks and plaza at the Boney Courthouse, located at 303 K St, Anchorage, Alaska, which was damaged during the November 2018 earthquake disaster.
Engineer's Estimate Range: Between $200,000 and $500,000
Additional Info:

FFY18 ST. PAUL AIRPORT VISUAL AID REPLACEMENT
Federal# / IRIS Program#: 3-02-0200-120-2018 / SFAPT00212
Region: Southcoast Region
Location: Regionwide
Manager: Peter J Jackson     Phone: (907)465-4439
Anticipate Advertising In: May 2022
Description of Work: Remove and replace secondary wind cone and install new conduit and wire. Remove and replace primary wind cone and install new conduit and wire. Remove and replace rotating Airport Beacon. Phase 4 - CC 24300206 LC 33004012
Engineer's Estimate Range: Between $200,000 and $500,000
Additional Info:

FFY18 VARIOUS PRIMARY/NON-PRIMARY EAS A/P VISUAL AID REPLCMN
Federal# / IRIS Program#: 3-02-0200-121-2018 / SFAPT00174
Region: Southcoast Region
Location: Regionwide
Manager: Peter J Jackson     Phone: (907)465-4439
Anticipate Advertising In: May 2022
Description of Work: Replace lighted beacon at Yakutat Airport.
Engineer's Estimate Range: Between $200,000 and $500,000
Additional Info: To be advertised with project SFAPT00203 (relocate Segmented Circle and Lighted Wind Cone).

FFY19 VARIOUS PRIMARY/NON PRIMARY EAS AIRPORTS VISUAL AID RE
Federal# / IRIS Program#: 3-02-0200-126-2019 / SFAPT00203
Region: Southcoast Region
Location: Regionwide
Manager: Peter J Jackson     Phone: (907)465-4439
Anticipate Advertising In: May 2022
Description of Work: Remove and relocate primary wind cone and segmented circle at Yakutat Airport including gravel pad and access road work.
Engineer's Estimate Range: Between $200,000 and $500,000
Additional Info: To be advertised with Project SFAPT00174

HSIP: A ST. MIDTOWN COUPLET OVERHEAD SIGNAL INDICATION U/G
Federal# / IRIS Program#: 0001684 / CFHWY00677
Region: Central Region
Location: Anchorage
Manager: Kevin L Jackson     Phone: (907)269-0610
Anticipate Advertising In: May 2022
Description of Work: Upgrade roadside hardware on A Street between Benson Boulevard and Northern Lights Boulevard. Work incudes removing and replacing the traffic signals at the intersection of Benson Boulevard and A Street and Northern Lights Boulevard and A Street and lighting system replacment adjacent to intersections.
Engineer's Estimate Range: Between $1,000,000 and $2,500,000
Additional Info:

JNU THANE ROAD 00039 - DEC 20 SE PR
Federal# / IRIS Program#: WILL BE FEMA RSA -DMV / SDRER00409
Region: Southcoast Region
Location: Juneau
Manager: Joel D Osburn     Phone: (907)465-4409
Anticipate Advertising In: May 2022
Description of Work: This project is a Permanent Repair (PR) due to flooding that occurred during the December, 2020 storm event in Southcoast Region of Alaska. Repairs may include, but are not limited to, asphalt, embankment, geotextile, riprap, and drainage. This project repairs a site on Thane Road at MPt 4.4. This is a FEMA funded project which will be reimbursed thru RSA with DMVA.
Engineer's Estimate Range: Between $500,000 and $1,000,000
Additional Info:

Northern Region ADA Improvements - Fairbanks: 6th Avenue
Federal# / IRIS Program#: 0002511 / NFHWY00551
Region: Northern Region
Location: Fairbanks North Star Borough
Manager: Ivet Hall     Phone: (907)451-5386
Anticipate Advertising In: May 2022
Description of Work: This project proposes to reconstruct ADA improvements and potentially widen the north sidewalk on the 6th Avenue in Fairbanks, Alaska. The project may also include reconstruction, roadside-hardware, drainage improvements, intersection improvements and utilities.
Engineer's Estimate Range: Between $500,000 and $1,000,000
Additional Info: Anticipated to advertise with NFHWY00504 project.
Preliminary Plans

Northern Region ADA Improvements - Fairbanks: Geist Road
Federal# / IRIS Program#: Pending / NFHWY00504
Region: Northern Region
Location: Fairbanks
Manager: Ivet Hall     Phone: (907)451-5386
Anticipate Advertising In: May 2022
Description of Work: This project proposes to reconstruct ADA improvements and potentially widen sidewalks on both sides of Geist Road within the project area in Fairbanks, Alaska. The project may also include reconstruction, roadside hardware, drainage improvements, intersection improvements and utilities.
Engineer's Estimate Range: Between $500,000 and $1,000,000
Additional Info: Anticipated to advertise with NFHWY00551 project.
Preliminary Plans

Northern Region Digital Message Signs (TAG)
Federal# / IRIS Program#: N/A / 25RC182609
Region: Northern Region
Location: Fairbanks North Star Borough
Manager: Ethan E Graetz     Phone: (907)451-2281
Anticipate Advertising In: May 2022
Description of Work: Install and operate digital messaging signs on the Parks Highway MP 357 and Richardson Highway MP 359.
Engineer's Estimate Range: Between $2,500,000 and $5,000,000
Additional Info:

SLEETMUTE AIRPORT RESURFACING
Federal# / IRIS Program#: 3-02-0272-001-2022 / CFAPT00293
Region: Central Region
Location: Sleetmute
Manager: Aaron C Hughes     Phone: (907)269-0523
Anticipate Advertising In: May 2022
Description of Work: The project will resurface the runway, taxiway, and apron, extend runway safety areas, and replace the snow removal equipment building. Improvements include airport lighting, tie-downs, drainage, dust palliative, visual NAVAIDs, and clearing.
Engineer's Estimate Range: Between $10,000,000 and $20,000,000
Additional Info: The project will resurface the runway, taxiway, and apron, extend runway safety areas, and replace the snow removal equipment building. Improvements include airport lighting, tie-downs, drainage, dust palliative, visual NAVAIDs, and clearing.

SR DM AIRPOR GATE/FENCE REPAIRS/REPLACEMENT
Federal# / IRIS Program#: N/A / SSAPT00093
Region: Southcoast Region
Location: Gustavus
Manager: Bran P Pollard     Phone: (907)465-4526
Anticipate Advertising In: May 2022
Description of Work: Replace an existing electric cantilever gate with a new 24’ electric vertical pivot gate on a new concrete foundation at the Gustavus Airport. Project gate will connect to the existing Airport Access Control System, existing automatic vehicle gate controllers, and existing auxiliary automatic vehicle gate safety control systems. Includes removal of existing 20' cantilever gate, removal of existing concrete foundation, and removal of existing fencing.
Engineer's Estimate Range: Less than $200,000
Additional Info:

YKCC Mechanical Upgrades Phase 2
Federal# / IRIS Program#: N/A / 25RC201621
Region: Central Region
Location: Bethel
Manager: Jesse Campbell     Phone: (907)269-0820
Anticipate Advertising In: May 2022
Description of Work: This State funded project will provide mechanical and boiler upgrades at the Yukon-Kuskokwim Correctional Center in Bethel, Alaska.
Engineer's Estimate Range: Between $500,000 and $1,000,000
Additional Info:

Copper River Boat Launch Facilities Improvements (FLAP)
Federal# / IRIS Program#: 0851072 / NFHWY00539
Region: Northern Region
Location: Mccarthy
Manager: Daniel S Adamczak     Phone: (907)451-2294
Anticipate Advertising In: June 2022
Description of Work: Improve the Copper River Boat Launch facilities located at MP 1.5 on the McCarthy Road. Work includes roadside hardware and drainage improvements.
Engineer's Estimate Range:
Additional Info:
Preliminary Plans

FAIRBANKS AREA PM 2.5 PLUG-INS: BIRCH HILL, CHENA LAKES, UAF
Federal# / IRIS Program#: N/A / NFHWY00627
Region: Northern Region
Location: Fairbanks North Star Borough
Manager: Ethan E Graetz     Phone: (907)451-2281
Anticipate Advertising In: June 2022
Description of Work: Provide electrical motor vehicle plug-ins at the following locations in the Fairbanks PM 2.5 non-attainment area: Birch Hill, Chena Lakes, and the UAF U-Park Building. Project includes utilities and drainage improvements.
Engineer's Estimate Range: Between $1,000,000 and $2,500,000
Additional Info:

HSIP: ANCHORAGE PEDESTRIAN LIGHTING
Federal# / IRIS Program#: 0001607 / CFHWY00366
Region: Central Region
Location: Anchorage
Manager: Christopher L Post     Phone: (907)269-7885
Anticipate Advertising In: June 2022
Description of Work: This HSIP Funded Project will increase visibility, reduce pedestrian/bicycle crashes and other traffic incidences by installing lighting. The proposed improvements are consistent with the Alaska Strategic Highway Safety Plan, Special Users Strategies to identify and implement appropriate engineering to address high-crash locations involving bicyclists and pedestrians. This project is also inline with MOA Vision Zero Safety Goals.
Engineer's Estimate Range: Between $1,000,000 and $2,500,000
Additional Info: This project will be advertised with CFHWY00132 Minnesota Dr Tudor to 15th Pavement Preservation. Preliminary Plans (~38 Mb)

JNU FRANKLIN AND THANE RESURFACING: TRAM PARKING LOT TO MT. ROBERTS ST
Federal# / IRIS Program#: 0003250 / SFHWY00263
Region: Southcoast Region
Location: Juneau
Manager: Darryl Lester     Phone: (907)465-4421
Anticipate Advertising In: June 2022
Description of Work: Resurface Franklin Street from the Tram parking lot to the intersection of Thane Road and Mt. Roberts Street. Associated preventive maintenance activities may include minor structural section improvements, drainage repairs, striping, signs, and ADA improvements.
Engineer's Estimate Range: Between $1,000,000 and $2,500,000
Additional Info: Pending funding availability. Advertisement may be delayed.

Ketchikan Pioneer Home Structural Upgrades
Federal# / IRIS Program#: N/A / 2501000083
Region: Central Region
Location: Central Region
Manager: Alyson K Wardell     Phone: (907)269-0869
Anticipate Advertising In: June 2022
Description of Work: Seismic upgrades for roof and building structure
Engineer's Estimate Range: Between $500,000 and $1,000,000
Additional Info: Advertise contingent upon funds by User Agency

KONGIGANAK AIRPORT IMPROVEMENTS
Federal# / IRIS Program#: 3-02-0380-004-2022 / CFAPT00433
Region: Central Region
Location: Kongiganak
Manager: Philip W Cheasebro     Phone: (907)269-0606
Anticipate Advertising In: June 2022
Description of Work: This project will rehabilitate airport surfaces, expand the apron and runway safety areas (RSA), install a Snow Removal Equipment Building (SREB) and relocate the existing SREB. Install a rotating beacon on a tip-down pole, tie-downs, and replace airfield lighting at the Kongiganak Airport. Expected FFY 2022 funding.
Engineer's Estimate Range: Between $20,000,000 and $30,000,000
Additional Info: Pre PS&E review documents are located at the link below: Preliminary Plans (~13 Mb)

MINNESOTA DR: TUDOR TO 15TH AVE PAVEMENT PRESERVATION
Federal# / IRIS Program#: 0421099 / CFHWY00132
Region: Central Region
Location: Anchorage
Manager: Steven J Rzepka     Phone: (907)269-0592
Anticipate Advertising In: June 2022
Description of Work: This is a Preventive Maintenance (PM) project for resurfacing Minnesota Drive in Anchorage, Alaska from Tudor Road to 15th Avenue. It will also include, as necessary: guardrail, drainage, signalization, ADA curb ramp improvements, signs and striping.
Engineer's Estimate Range: Between $10,000,000 and $20,000,000
Additional Info: This project will be advertised with CFHWY00366 HSIP Anchorage Pedestrian Lighting. Preliminary Plans (~27 Mb)

North Pole City Core Streetlight Standardization and Improvements
Federal# / IRIS Program#: N/A / NFHWY00690
Region: Northern Region
Location: North Pole
Manager: Ethan E Graetz     Phone: (907)451-2281
Anticipate Advertising In: June 2022
Description of Work: Replace the lighting system with more energy efficient technologies and install new LED luminaires. Work will include roadside hardware and utilities.
Engineer's Estimate Range: Between $1,000,000 and $2,500,000
Additional Info:

Point Hope Airport Realignment
Federal# / IRIS Program#: 3-02-0226-___-____ / Z638420000
Region: Northern Region
Location: Point Hope
Manager: Jonathan J Hutchinson     Phone: (907)451-5479
Anticipate Advertising In: June 2022
Description of Work: Realign the runway at the Point Hope Airport.
Engineer's Estimate Range: Between $10,000,000 and $20,000,000
Additional Info:
Preliminary Plans

Saint Mary's Airport Improvements
Federal# / IRIS Program#: PENDING / Z605630000
Region: Northern Region
Location: St Mary's
Manager: Christopher F Johnston     Phone: (907)451-2322
Anticipate Advertising In: June 2022
Description of Work: Rehabilitate and resurface runways, taxiways, and apron. Project will include replacing airport lighting and runway safety area improvements.
Engineer's Estimate Range: Between $20,000,000 and $30,000,000
Additional Info:
Preliminary Plans

Shishmaref Airport Erosion Control
Federal# / IRIS Program#: 3-02-0404-___-____ / NFAPT00370
Region: Northern Region
Location: Shishmaref
Manager: Jonathan J Hutchinson     Phone: (907)451-5479
Anticipate Advertising In: June 2022
Description of Work: Install erosion protection at the Shishmaref Airport.
Engineer's Estimate Range: Between $10,000,000 and $20,000,000
Additional Info: 22E
Preliminary Plans

SIT AIRPORTEQ BLDG REHAB
Federal# / IRIS Program#: N/A / SFAPT00363
Region: Southcoast Region
Location: Sitka
Manager: Jesse Campbell     Phone: (907)269-0820
Anticipate Advertising In: June 2022
Description of Work: Rehabilitation of existing combined use equipment building to include siding replacement, equipment bay door replacements, heating system replacement, and building envelope improvements
Engineer's Estimate Range: Between $1,000,000 and $2,500,000
Additional Info:

ANC TAXIWAY Z IMPROVEMENTS WEST - PHASE 1
Federal# / IRIS Program#: 3-02-0016-218-2022 / CFAPT00465
Region: Central Region
Location: Anchorage
Manager: Philip W Cheasebro     Phone: (907)269-0606
Anticipate Advertising In: July 2022
Description of Work: This Federally Funded contract provides geometric upgrades as necessary to accommodate larger ADG VI, TDG 6 aircraft. The proposed geometric upgrades include widening Taxiway's Z & E, constructing a new entrance Taxiway R, and rehabilitating Taxilane's R & E. Additional work includes: • Rehabilitate or relocate existing private taxilane approaches as needed • Remove TW F entrance taxiway • Relocate existing service road • Drainage improvements • Replace taxiway lighting and sign and install new lights and signs as needed • Relocate/adjust utilities as needed • Relocate/adjust FAA NAVAIDS as needed
Engineer's Estimate Range: Between $20,000,000 and $30,000,000
Additional Info: Pre PS&E review documents are located at the link: Preliminary Plans (~46 Mb)

Colleen Street Intersection and Frontage Road
Federal# / IRIS Program#: 0A15033 / CFHWY00006
Region: Central Region
Location: Palmer
Manager: Sean M Baski     Phone: (907)269-0566
Anticipate Advertising In: July 2022
Description of Work: Construct improvements to the Glenn Highway and South Colleen Street intersection, and improve connectivity and access.
Engineer's Estimate Range: Between $2,500,000 and $5,000,000
Additional Info: Preliminary Plans (~37 Mb)

Dalton Hwy MP 18-37 Reconstruction
Federal# / IRIS Program#: 0652017 / Z607350000
Region: Northern Region
Location: Northern Region
Manager: Carl F Heim     Phone: (907)451-5359
Anticipate Advertising In: July 2022
Description of Work: Reconstruct the Dalton Highway from Milepost 18 to 37. The project work includes bridge work, roadside hardware and drainage improvements. Bridge work includes Hess Creek Bridge #1213 replacement.
Engineer's Estimate Range: Between $50,000,000 and $60,000,000
Additional Info:
Preliminary Plans
Reports

Deering Airport Improvements
Federal# / IRIS Program#: 3-02-0400-XX-202X / NFAPT00249
Region: Northern Region
Location: Deering
Manager: Jonathan J Hutchinson     Phone: (907)451-5479
Anticipate Advertising In: July 2022
Description of Work: Resurface the existing runway, taxiway and apron and provide drainage improvements. Upgrade lighting system and electrical building. Provide erosion protection for the runway safety area at Runway 29. Replace segmented circle. Upgrade and armor the airport access road to reduce flooding and provide cross drainage. Apply dust palliative to all airport operational surfaces and access road.
Engineer's Estimate Range: Between $10,000,000 and $20,000,000
Additional Info:

Glenn Hwy: Parks Hwy to S. Inner Springer Lp. (Phase II)
Federal# / IRIS Program#: 0A15037 / CFHWY00431
Region: Central Region
Location: Palmer
Manager: Sean M Baski     Phone: (907)269-0566
Anticipate Advertising In: July 2022
Description of Work: This project will reconstruct the Glenn Highway from the Parks Highway to S. Inner Springer Loop as a four-lane divided highway. Project work will add lanes, widen shoulders, add turn lanes and frontage roads, signals, illumination, other traffic safety related improvements.
Engineer's Estimate Range: Between $20,000,000 and $30,000,000
Additional Info: Preliminary Plans (~54 Mb)

Glenn Hwy: Parks to S. Inner Springer Lp. Pathway (Phase II)
Federal# / IRIS Program#: 0A15038 / CFHWY00432
Region: Central Region
Location: Palmer
Manager: Sean M Baski     Phone: (907)269-0566
Anticipate Advertising In: July 2022
Description of Work: This project will construct a pathway along the Glenn Highway and other roads. It also includes roadside hardware and drainage, intersection, and ADA improvements. This project will construct the second phase of the Glenn Hwy: Mile Post 34-42 Parks to Old Glenn Pathway project.
Engineer's Estimate Range: Between $1,000,000 and $2,500,000
Additional Info: Preliminary Plans (~54 Mb) Please note, this project will be advertising with project number CFHWY00431.

HNS MOSQUITO LAKE ROAD #550474 - DEC 20 SE PR
Federal# / IRIS Program#: PENDING FEMA RSA -DMV / SDRER00408
Region: Southcoast Region
Location: Haines
Manager: Joel D Osburn     Phone: (907)465-4409
Anticipate Advertising In: July 2022
Description of Work: This project will permanently repair damage on Mosquito Lake Road caused by the December 2020 storm event in Southeast Alaska. The project includes repairing an embankment failure and replacing a damaged culvert. This is a FEMA funded project which will be reimbursed thru RSA with DMVA
Engineer's Estimate Range: Between $200,000 and $500,000
Additional Info:

HOMER AIRPORT IMPROVEMENTS
Federal# / IRIS Program#: AIP 3-02-0122-020-2022 / CFAPT00491
Region: Central Region
Location: Homer
Manager: Matthew H Hansen     Phone: (907)269-0602
Anticipate Advertising In: July 2022
Description of Work: The project proposes to rehabilitate the runway and runway safety area; remove obstructions; rehabilitate Taxiways A & B; rehabilitate and expand the General Aviation apron toward the east; replace airfield lighting, remove Taxiway D; install a new turnaround taxiway at the east end of the runway, and install a new taxiway connecting the east end of the General Aviation apron to the runway.
Engineer's Estimate Range: Between $20,000,000 and $30,000,000
Additional Info: Preliminary Plans (~22 Mb)

HSIP KTN STEDMAN & DEERMOUNT ST INTERSECTION SAFETY IMP
Federal# / IRIS Program#: 0003244 / SFHWY00186
Region: Southcoast Region
Location: Ketchikan
Manager: Nathan A Purves     Phone: (907)465-4521
Anticipate Advertising In: July 2022
Description of Work: Provide additional illumination at the Stedman/Deermount intersection to achieve a level of luminance that meets current DOT&PF standards. Construct a concrete sidewalk bulbout on the Stedman side of the marked crosswalk. The bulbout will extend from the existing sidewalk to the edge of the traveled way.
Engineer's Estimate Range: Between $500,000 and $1,000,000
Additional Info:

Mchugh RWIS Tower Upgrade
Federal# / IRIS Program#: 0106(094) / CFHWY00428
Region: Central Region
Location: Municipality Of Anchorage
Manager: John W Turley     Phone: (907)266-2171
Anticipate Advertising In: July 2022
Description of Work: RWIS facilities must be migrated off of the existing tower at McHugh MP 111.8 of the Seward Highway. The existing tower will be demolished and a new tower will be installed within DOT ROW.
Engineer's Estimate Range: Between $200,000 and $500,000
Additional Info:

Mt. Edgecumbe High School Building 290 Kitchen Make-up Air & Exhaust Fan Replacement
Federal# / IRIS Program#: N/A / 25RC053613
Region: Central Region
Location: Sitka
Manager: Christopher S Hodgin     Phone: (907)269-7484
Anticipate Advertising In: July 2022
Description of Work: This state funded project includes the demolition of the existing kitchen make-up air and exhaust systems and replacement with new systems, at the Mt. Edgecumbe High School Campus in Sitka, Alaska
Engineer's Estimate Range: Between $200,000 and $500,000
Additional Info:

PSG Mitkof Hwy MPt 10.8 Culvert Replacement - DEC 20 SE PR
Federal# / IRIS Program#: AK2021-1 / SFHWY00379
Region: Southcoast Region
Location: Petersburg
Manager: Joel D Osburn     Phone: (907)465-4409
Anticipate Advertising In: July 2022
Description of Work: This project is a Permanent Repair (PR) due to flooding that occurred during the December, 2020 storm event in the Southcoast Region of Alaska. The project need is to replace the existing 5.5' diameter culvert at Mitkof Highway milepoint (MPt) 10.8 to current standards and provide slope and road stability with a new 7' diameter culvert. Repairs may include, but are not limited to, asphalt, embankment, riprap, and drainage. This project repairs sites corresponding to Detailed Damage Inspection Report DDIR AK 2020 01 PTG001.
Engineer's Estimate Range: Between $1,000,000 and $2,500,000
Additional Info:

SGY STATE STREET PAVEMENT REHABILITATION
Federal# / IRIS Program#: 0972018 / Z680850000
Region: Southcoast Region
Location: Skagway
Manager: David A Pyeatt     Phone: (907)465-4490
Anticipate Advertising In: July 2022
Description of Work: Rehabilitate the pavement, replace curb and gutter in select areas, upgrade curb ramps and vehicular curb cuts to meet ADA standards, repair and/or replace drainage facilities as needed, and replace all signs within the project limits.
Engineer's Estimate Range: Between $20,000,000 and $30,000,000
Additional Info: Rehabilitate the pavement from 1st Avenue to the Skagway River Bridge. Repair and/or replace existing drainage infrastructure. Replace existing sidewalk, curb ramps, and driveways to meet current ADA requirements.

AMATS: HILAND RD MP 0 TO MP 3.2 PAVEMENT PRESERVATION
Federal# / IRIS Program#: 0001663 / CFHWY00568
Region: Central Region
Location: Eagle River
Manager: Galen K Jones     Phone: (907)269-0550
Anticipate Advertising In: August 2022
Description of Work: Resurface Hiland Road, including milling, paving, minor subgrade rehabilitation, drainage improvements, updating guardrail and sign posts to meet current safety standards, replacing striping and select signage, curb and gutter, lighting, and roadside signal and or traffic data hardware.
Engineer's Estimate Range: Between $2,500,000 and $5,000,000
Additional Info:

ANC Parking Garage PG111 Repairs and Improvement
Federal# / IRIS Program#: N/A / CSAPT00566
Region: Central Region
Location: Anchorage
Manager: John W Turley     Phone: (907)266-2171
Anticipate Advertising In: August 2022
Description of Work: This project will replace the roof membrane on the roof level of PG-111. Parking Garage and will make repairs to floor deck spalling and electric lighting that have resulted from water infiltration.
Engineer's Estimate Range:
Additional Info:

HNH SEAPLANE FACILITY DREDGING AND CREEK RELOCATION
Federal# / IRIS Program#: N/A / SFAPT00236
Region: Southcoast Region
Location: Hoonah
Manager: Loren K Gehring     Phone: (907)465-8189
Anticipate Advertising In: August 2022
Description of Work: Relocation of an existing stream bed and conduct dredging under the seaplane mooring float to restore sufficient water depths and/or relocation of the seaplane float structure to deeper water at the same location. Phase: T02000 - Par - All Costs
Engineer's Estimate Range: Between $500,000 and $1,000,000
Additional Info: Construction funding uncertain.

JNU DOUGLAS HIGHWAY SLOPE STABILIZATION
Federal# / IRIS Program#: 0959021 / SFHWY00163
Region: Southcoast Region
Location: Juneau
Manager: David A Pyeatt     Phone: (907)465-4490
Anticipate Advertising In: August 2022
Description of Work: Repair a recent slope failure adjacent to a soldier pile and lagging retaining wall along the Juneau-Douglas Highway, in Douglas, Alaska. The slope failure impacted adjacent property and exposed the solider pile and lagging wall supporting the Juneau-Douglas Highway and pedestrian pathway. The purpose of the project is to protect the highway slope from failure due to down slope landslide activity out of the ROW by constructing a soldier pile wall.
Engineer's Estimate Range: Between $1,000,000 and $2,500,000
Additional Info: Project to be advertised with SFHWY00315.

JNU DOUGLAS HWY STAGE 2 CONSTRUCTION
Federal# / IRIS Program#: 958032 / SFHWY00315
Region: Southcoast Region
Location: Juneau
Manager: David A Pyeatt     Phone: (907)465-4490
Anticipate Advertising In: August 2022
Description of Work: Work required for this project includes reconstructing and resurfacing Douglas Highway from about 700 feet south of Cordova Street to F Street. Other work includes ADA improvements, storm drain system repairs, signing and striping improvements, and bridge joint repairs. A list of anticipated work items are listed below: • Pavement removal and roadway excavation • Pavement cold planing • Removal and installation of concrete gutter and curb & gutters • Removal and installation of asphalt and concrete sidewalks • Reconstruction of existing accessible sidewalk ramps • Replacement and lining of existing culverts and storm drains • Construction of riprap aprons • Installation of new curb inlets • Removal and installation of storm drain manholes • Replacement of existing signs • Addition of new signs • New pavement markings • Replacement of existing guardrail and bridge transition rail • Repairs to existing Lawson Creek Bridge joints • Replacement of wood planter box and steps with concrete retaining wall and wood stairs at Villa Gastineau Condos
Engineer's Estimate Range: Between $10,000,000 and $20,000,000
Additional Info:

JNU EGAN YANDUKIN INTERSECTION IMPROVEMENTS HSIP
Federal# / IRIS Program#: 0003261 / SFHWY00307
Region: Southcoast Region
Location: Juneau
Manager: Nathan A Purves     Phone: (907)465-4521
Anticipate Advertising In: August 2022
Description of Work: Set seasonal speed limit reduction on Egan in the vicinity of the Egan Yandukin intersection. Improve delineation for both left turns on Egan to improve line of sight and reduce travel distance to clear opposing traffic. Improve delineation for the northbound right turn movement from Egan to make it easier for southbound left turn drivers to determine if opposing traffic is executing the right turn or continuing through the intersection.
Engineer's Estimate Range: Between $1,000,000 and $2,500,000
Additional Info:

JNU N DGLS HWY: BONNIE BRAE-DEC 20 SE PR
Federal# / IRIS Program#: 0093002 / SFHWY00411
Region: Southcoast Region
Location: Juneau
Manager: Joel D Osburn     Phone: (907)465-4409
Anticipate Advertising In: August 2022
Description of Work: This project will design and construct permanent repairs (PR) to assets damaged by the December 2020 Storm in the Southcoast Region of Alaska for DDIR AK 2021 01 PTG001. Repairs may include, but are not limited to, asphalt, embankment, geotextile, riprap, drainage, roadside hardware, and utilities. This project will repair a site on the North Douglas Highway near Bonnie Brae Subdivision.
Engineer's Estimate Range: Between $500,000 and $1,000,000
Additional Info:

KTN FERRY TERMINAL IMPROVEMENTS (X-REF#SAMHS00015)
Federal# / IRIS Program#: 000S855 / Z674660000
Region: Marine Highways
Location: Ketchikan
Manager: Loren K Gehring     Phone: (907)465-8189
Anticipate Advertising In: August 2022
Description of Work: This project encompasses the replacement of an existing vessel berthing and turning dolphin structure at the west end of Berth 1; placement of a new turning dolphin between Berths 1 and 3, refurbishment of fendering and platform components at the Berth 3 float; construction of a new pedestrian cover structure over the existing sidewalk from the terminal building to the Berth 3 approach; and the placement of cathodic protection anodes on all existing offshore pile supported structures at Berths 1 and 3.
Engineer's Estimate Range: Between $2,500,000 and $5,000,000
Additional Info: Refurbish fender system at Berth 3 and conduct minor improvements to utilities at Berth 1.

SGY DYEA ROAD 189468 - DEC 20 SE PR
Federal# / IRIS Program#: WILL BE FEMA RSA -DMV / SDRER00410
Region: Southcoast Region
Location: Skagway
Manager: Joel D Osburn     Phone: (907)465-4409
Anticipate Advertising In: August 2022
Description of Work: This project is a Permanent Repair (PR) due to flooding that occurred during the December, 2020 storm event in Southcoast Region of Alaska. Repairs may include, but are not limited to, asphalt, embankment, roadside hardware, retaining walls utilities, and drainage. May include mitigation to prevent future similar damage to facilities. This project repairs sites on Dyea Road at FEMA Damage Inventory Numbers 461214,461216, 461217,461260,461261,461648,784616, and 784619. This is a FEMA funded project which will be reimbursed thru RSA with DMVA
Engineer's Estimate Range: Between $2,500,000 and $5,000,000
Additional Info:

STERLING HWY: MP 157-169 RECON-ANCHOR PT TO BAYCREST HILL
Federal# / IRIS Program#: 0211052 / Z581060000
Region: Central Region
Location: Kenai Peninsula
Manager: Kelly L Summers     Phone: (907)269-0546
Anticipate Advertising In: August 2022
Description of Work: Reconstruction and upgrading of 12 miles of Sterling Highway along existing corridor. Project upgrades include widening, construction of passing lanes, resurfacing, scenic turnouts, drainage improvements, minor realignment, and configuration to current AASHTO geometric standards. Also, rehabilitation/replacement of the North Fork Anchor River and Anchor River Bridges.
Engineer's Estimate Range: Between $80,000,000 and $90,000,000
Additional Info: Reconstruct and upgrade 12 miles of the Sterling Hwy along the existing corridor from Anchor Pt to Baycrest Hill. Replacement of North Fork Anchor River and Anchor River Bridges. Project upgrades include widening, construction of passing lanes, resurfacing, drainage improvements, minor realignment, and configuration to current AASHTO geometric standards.

ANC TW K and TL E Apron Rehabilitation
Federal# / IRIS Program#: N/A / CFAPT00855
Region: Central Region
Location: Anchorage
Manager: Jennifer M Carle     Phone: (907)266-2731
Anticipate Advertising In: September 2022
Description of Work: Rehabilitate the apron surface. Project will include striping.
Engineer's Estimate Range: Between $500,000 and $1,000,000
Additional Info: Rehabilitate Apron Surface

JNU KAXDIGOOWU HEEN DEI IMP (BROTHERHOOD BRIDGE TRAIL IMP)
Federal# / IRIS Program#: TA18010 / SFHWY00259
Region: Southcoast Region
Location: Juneau
Manager: Peter J Jackson     Phone: (907)465-4439
Anticipate Advertising In: September 2022
Description of Work: This project will design and improve the Kaxdigoowu Heen Dei (Kax) Trail from River Road to the edge of Brotherhood Meadow, where a re-route planned for construction in 2019 would end, and create a new segment of paved trail that connects from the edge of Brotherhood Meadow to the Wildmeadow Neighborhood and the newly constructed trail from Pederson Hill neighborhood. Work will primarily consist of selected areas of subgrade repair, repave the 8 foot wide trail, replace and add new culverts as needed, and build approximately 1,500 feet of new trail section. The new trail will be composed of fill, D-1, and 8 foot wide asphalt with 1 foot shoulders. the pedestrian bridge at Montana Creek will be replaced or modified to provide a larger span that allows for some natural stream movement and can withstand emergency and maintenance vehicle use once again, and the banks armored to increase the expected useful life of the bridge. Additional improvements include adding bike racks, installing interpretive signs, and increasing site distance along the trail.
Engineer's Estimate Range: Between $1,000,000 and $2,500,000
Additional Info:

MAT-SU BOROUGH ROAD REPAIRS - NOV 2018 EQ PERM REPAIRS (MSB)
Federal# / IRIS Program#: 0092010 / CFHWY00648
Region: Central Region
Location: Matanuska-Susitna Borough
Manager: Steven J Rzepka     Phone: (907)269-0592
Anticipate Advertising In: September 2022
Description of Work: This project will design and construct repairs for the November 30, 2018 earthquake in the Central Region of Alaska on Point MacKenzie Road, Vine Road, and South Settlers Bay Drive. Repairs may include, but are not limited to, asphalt, embankment, roadside hardware, retaining walls, utilities, and drainage.
Engineer's Estimate Range: Between $5,000,000 and $10,000,000
Additional Info:

POW HOLLIS HWY GUARDRAIL SAFETY IMPROVEMENTS HSIP
Federal# / IRIS Program#: 0003260 / SFHWY00306
Region: Southcoast Region
Location: Prince Of Wales Island
Manager: Nathan A Purves     Phone: (907)465-4521
Anticipate Advertising In: September 2022
Description of Work: Determine the extent of the zone where we can expect a driver to recover control of there vehicle and remove/replace downstream guardrail end anchors that fall in that zone with guardrail parallel end terminals that are compliant with the Manual for Assessing Safety Hardware 16 (MASH16).
Engineer's Estimate Range: Between $500,000 and $1,000,000
Additional Info:

CTF ALTERNATE ENTRANCE ALIGNMENT (WFL)
Federal# / IRIS Program#: AKBLM AFO 2014(1) / CFHWY00260
Region: Central Region
Location: Anchorage
Manager: Christopher L Post     Phone: (907)269-7885
Anticipate Advertising In: October 2022
Description of Work: Relocate the BLM Road to the Cambell Tract Facility 260 feet to align East 68th Avenue with intersection improvements to include bus stop and integration to existing signalized intersection.
Engineer's Estimate Range: Between $2,500,000 and $5,000,000
Additional Info:

DEARMOUN RD: E 140TH AVE - HILLSIDE DR PAVEMENT PRESERVATION
Federal# / IRIS Program#: 0510007 / CFHWY00286
Region: Central Region
Location: Anchorage
Manager: Jon W Knowles     Phone: (907)269-0643
Anticipate Advertising In: October 2022
Description of Work: Pavement Preservation of DeArmoun Rd. from East 140th Avenue to Hillside Drive including improvements to drainage, intersections, ADA, roadside hardware, and utilities. High Friction Surface Treatment may be reapplied.
Engineer's Estimate Range: Between $2,500,000 and $5,000,000
Additional Info:

EDGERTON HWY MP 24 - 29 RESURFACING
Federal# / IRIS Program#: 0850030 / NFHWY00587
Region: Northern Region
Location: Mccarthy
Manager: John J Netardus     Phone: (907)451-5448
Anticipate Advertising In: October 2022
Description of Work: Resurface the Edgerton Highway from MP 24 - 29. Project will include drainage improvements, roadside hardware, and utilities.
Engineer's Estimate Range:
Additional Info:

ELMORE ROAD PAVEMENT PRESERVATION: ABBOTT RD TO PROVIDENCE
Federal# / IRIS Program#: 0001642 / CFHWY00395
Region: Central Region
Location: Anchorage
Manager: Christopher L Post     Phone: (907)269-7885
Anticipate Advertising In: October 2022
Description of Work: Pavement Preservation project for Elmore Road: Abbott Rd. to Providence Dr. This project includes resurfacing, roadside hardware, drainage improvements, intersection improvements, and ADA improvements as necessary.
Engineer's Estimate Range: Between $10,000,000 and $20,000,000
Additional Info:

FUNNY RIVER RD PAVEMENT PRESERVATION
Federal# / IRIS Program#: 0485002 / CFHWY00493
Region: Central Region
Location: Kenai
Manager: Steven J Rzepka     Phone: (907)269-0592
Anticipate Advertising In: October 2022
Description of Work: Pavement preservation, bridge work, roadside hardware, drainage improvements, intersection improvements, ADA improvements and utilities.
Engineer's Estimate Range: Between $10,000,000 and $20,000,000
Additional Info: Pavement preservation, bridge work, roadside hardware, drainage improvements, intersection improvements, ADA improvements and utilities.

KTN - WATER ST TRESTLE #1 IMPRVMNT
Federal# / IRIS Program#: 0003224 / SFHWY00069
Region: Southcoast Region
Location: Ketchikan
Manager: Kirk D Miller     Phone: (907)465-1215
Anticipate Advertising In: October 2022
Description of Work: Replace the Water Street Trestle No. 1 bridge structure with (No. 389) with MSE wall. Work includes new utilities, pavement and sidewalks.
Engineer's Estimate Range: Between $1,000,000 and $2,500,000
Additional Info:

LHD AIRCRAFT AND LAKESHORE DRIVE REHABILITATION
Federal# / IRIS Program#: N/A / CFAPT00882
Region: Central Region
Location: Anchorage
Manager: Jennifer M Carle     Phone: (907)266-2731
Anticipate Advertising In: October 2022
Description of Work: Rehabilitate 9,600 ft of Aircraft and Lakeshore Dr from Voight Cir to the Lake Hood East property boundary south of runway 14/32. Project includes roadway reconditioning, structural section repairs, drainage improvements, and striping.
Engineer's Estimate Range: Between $1,000,000 and $2,500,000
Additional Info: Rehabilitate Aircraft and Lakeshore Drive pavement. Includes drainage improvements.

Nome Port Road Reconstruction
Federal# / IRIS Program#: 0002278 / Z621230000
Region: Northern Region
Location: Nome
Manager: Lauren M Little     Phone: (907)378-5911
Anticipate Advertising In: October 2022
Description of Work: Reconstruct and realign Port Road in Nome, including drainage improvements and construction of sidewalks.
Engineer's Estimate Range: Between $2,500,000 and $5,000,000
Additional Info:
Preliminary Plans

ANC ACCESS GATE, HEADBOLT OUTLETS, AND DITCH GRADING
Federal# / IRIS Program#: N/A / CSAPT00931
Region: Central Region
Location: Anchorage
Manager: Jennifer M Carle     Phone: (907)266-2731
Anticipate Advertising In: November 2022
Description of Work: Project will include: 1) constructing a new vehicle access control gate at AFM West; 2) install head bolt outlets (HBO) at the TW A and DeHavilland Avenue snow disposal sites; and 3) re-grade the tug road ditch south of the Trans-northern lease lot.
Engineer's Estimate Range: Between $500,000 and $1,000,000
Additional Info:

EAST COLLEGE ROAD RESURFACING
Federal# / IRIS Program#: 0640013 / NFHWY00645
Region: Northern Region
Location: Fairbanks
Manager: Russell M Johnson     Phone: (907)451-5059
Anticipate Advertising In: November 2022
Description of Work: Resurface College Road between the Margaret/Antoinette and Old Steese Highway intersections including the College Road/Johansen Expressway Interchange on and off ramps. Project will include ADA and drainage improvements, pavement preservation, roadside hardware, and utilities.
Engineer's Estimate Range: Between $2,500,000 and $5,000,000
Additional Info: Project is anticipated to be combined with NFHWY00591 Northern Region ADA Improvements - Fairbanks: College Road

ELLIOTT HIGHWAY MP 18 - 29 RESURFACING
Federal# / IRIS Program#: 0650035 / NFHWY00588
Region: Northern Region
Location: Livengood
Manager: John J Netardus     Phone: (907)451-5448
Anticipate Advertising In: November 2022
Description of Work: Resurface the Elliott Highway from MP 18 - 29. Project will include selected areas of roadway rehabilitation, bridge work, drainage improvements, roadside hardware, and utilities.
Engineer's Estimate Range:
Additional Info:

HSIP: CR GUARDRAIL INVENTORY AND UPGRADE
Federal# / IRIS Program#: 0001665 / CFHWY00564
Region: Central Region
Location: Central
Manager: Chris L Bentz     Phone: (907)269-0652
Anticipate Advertising In: November 2022
Description of Work: Prepare inventory by evaluating existing guardrail segments, end terminals, and associated hardware along several routes in Central Region for damage and adherence to current AKDOT&PF and FHWY standards. Use results of inventory to design and construct installation or updates to guardrail segments found in non- conformance with State and Federal standards.
Engineer's Estimate Range: Between $20,000,000 and $30,000,000
Additional Info:

HSIP:CR Guardrail Inventory and Upgrade (North)
Federal# / IRIS Program#: N/A / CFHWY00939
Region: Central Region
Location: Central Region
Manager: Chris L Bentz     Phone: (907)269-0652
Anticipate Advertising In: November 2022
Description of Work: Prepare inventory by evaluating existing guardrail segments, end terminals, and associated hardware along several routes in Central Region for damage and adherence to current AKDOT&PF and FHWA standards. Use results of inventory to design and construct installation or updates to guardrail segments found in non-conformance with State and Federal standards.
Engineer's Estimate Range:
Additional Info:

HSIP:CR Guardrail Inventory and Upgrade (South)
Federal# / IRIS Program#: N/A / CFHWY00938
Region: Central Region
Location: Central Region
Manager: Chris L Bentz     Phone: (907)269-0652
Anticipate Advertising In: November 2022
Description of Work: Prepare inventory by evaluating existing guardrail segments, end terminals, and associated hardware along several routes in Central Region for damage and adherence to current AKDOT&PF and FHWY standards. Use results of inventory to design and construct installation or updates to guardrail segments found in non- conformance with State and Federal standards.
Engineer's Estimate Range:
Additional Info:

JNU DOUGLAS HWY RESURFACE & SIDEWALK REPAIRS STAGE III
Federal# / IRIS Program#: 0958032 / SFHWY00058-3
Region: Southcoast Region
Location: Juneau
Manager: David A Pyeatt     Phone: (907)465-4490
Anticipate Advertising In: November 2022
Description of Work: Work required for this project includes reconstructing and resurfacing Douglas Highway from Egan Drive to about 700 feet south of Cordova Street. Other work includes ADA improvements, storm drain system repairs, signing and striping improvements, and bridge joint repairs. A list of anticipated work items are listed below: • Pavement removal and roadway excavation • Pavement cold planing • Removal and installation of concrete gutter and curb & gutters • Removal and installation of asphalt and concrete sidewalks • Reconstruction of existing accessible sidewalk ramps • Replacement and lining of existing culverts and storm drains • Construction of riprap aprons • Installation of new curb inlets • Removal and installation of storm drain manholes • Replacement of existing signs • Addition of new signs • New pavement markings • Replacement of existing guardrail and bridge transition rail
Engineer's Estimate Range: Between $2,500,000 and $5,000,000
Additional Info:

Northern Region ADA Improvements - Fairbanks: College Road
Federal# / IRIS Program#: N/A / NFHWY00591
Region: Northern Region
Location: Fairbanks
Manager: Ivet Hall     Phone: (907)451-5386
Anticipate Advertising In: November 2022
Description of Work: Reconstruct pedestrian facilities and adjacent areas on sections of College Road in Fairbanks. Project includes drainage improvements.
Engineer's Estimate Range: Between $1,000,000 and $2,500,000
Additional Info: Project is anticipated to be combined with NFHWY00645 East College Road Resurfacing.

Richardson Highway MP 128-138 Rehabilitation
Federal# / IRIS Program#: Pending / NFHWY00265
Region: Northern Region
Location: Tazlina
Manager: Russell M Johnson     Phone: (907)451-5059
Anticipate Advertising In: November 2022
Description of Work: Rehabilitate the Richardson Highway and bridges between MP 128 and MP 138. Project work will include road realignment at MP 134, drainage improvements, intersection improvements, and roadside hardware.
Engineer's Estimate Range:
Additional Info:

WRG ZIMOVIA HWY ROCK FALL MITIGATION HSIP
Federal# / IRIS Program#: 0003262 / SFHWY00308
Region: Southcoast Region
Location: Wrangell
Manager: Nathan A Purves     Phone: (907)465-4521
Anticipate Advertising In: November 2022
Description of Work: Perform slope stabilization and mitigation work at two rock fall sites on Zimovia Highway in Wrangell, Alaska.
Engineer's Estimate Range: Between $500,000 and $1,000,000
Additional Info:

KTN TONGASS AVE IMPROVEMENTS
Federal# / IRIS Program#: 0902042 / Z680910000
Region: Southcoast Region
Location: Ketchikan
Manager: Peter J Jackson     Phone: (907)465-4439
Anticipate Advertising In: December 2022
Description of Work: Refurbish Tongass Avenue, from MP 0.2010 to 1.2565 including rehabilitation of asphalt and concert pavement surfaces, curb and gutter, sidewalk, correct ADA deficiencies, make improvements to the signalization, lane configurations, and to the pedestrian and bicycle facilities to improve safety and level of service.
Engineer's Estimate Range: Between $5,000,000 and $10,000,000
Additional Info:

MEKORYUK AIRPORT REHABILITATION
Federal# / IRIS Program#: 3-02-0176-003-2022 / CFAPT00288
Region: Central Region
Location: Mekoryuk
Manager: Philip W Cheasebro     Phone: (907)269-0606
Anticipate Advertising In: December 2022
Description of Work: Rehabilitate/reconstruct runway, taxiway, and access road. Install new lighting. Install new heated two-bay SREB and install dust palliative.
Engineer's Estimate Range: Between $20,000,000 and $30,000,000
Additional Info: Pre PS&E review documents are located at the link: Preliminary Plans (~20 Mb)

NOR REG VARIOUS AIRPORTS VISUAL AID REPLACEMENT FFY2020
Federal# / IRIS Program#: N/A / NFAPT00537
Region: Northern Region
Location: Regionwide
Manager: Daniel A Phillips     Phone: (907)451-2926
Anticipate Advertising In: December 2022
Description of Work: Replace visual aids at the following airports: Beaver, Birch Creek, Elim, and Koyuk.
Engineer's Estimate Range:
Additional Info:

Richardson Hwy MP 167-173
Federal# / IRIS Program#: 0713010 / Z631860000
Region: Northern Region
Location: Paxson
Manager: Russell M Johnson     Phone: (907)451-5059
Anticipate Advertising In: December 2022
Description of Work: Reconstruct the Richardson Highway between MP 167 and 173. Project includes roadside hardware, drainage improvements and utility relocations.
Engineer's Estimate Range: Between $20,000,000 and $30,000,000
Additional Info: Reconstruct the Richardson Highway between mileposts 167-173.

RICHARDSON HWY MP 266-341 PASSING LANES
Federal# / IRIS Program#: 0A23021 / Z607150000
Region: Northern Region
Location: Fairbanks North Star Borough
Manager: Carl F Heim     Phone: (907)451-5359
Anticipate Advertising In: December 2022
Description of Work: Construct passing lanes at multiple locations between Milepost 266 and 341 on the Richardson Highway. Work includes roadside hardware, drainage improvements, intersection improvements and utilities.
Engineer's Estimate Range: Between $30,000,000 and $40,000,000
Additional Info:

ANC RON 3 AND 4 JOINT REPAIRS
Federal# / IRIS Program#: N/A / CSAPT00754
Region: Central Region
Location: Anchorage
Manager: Jennifer M Carle     Phone: (907)266-2731
Anticipate Advertising In: January 2023
Description of Work: Remove and replace approximately 15,000 feet of liquid joint seal and perform approximately 300 square feet of elastomeric concrete repairs on hardstands RON 3 and 4.
Engineer's Estimate Range: Between $1,000,000 and $2,500,000
Additional Info: Repair joints and concrete on hardstands 3 & 4.

ANC TAXIWAY R SOUTH SURFACE SEAL
Federal# / IRIS Program#: N/A / CFAPT00758
Region: Central Region
Location: Anchorage
Manager: Jennifer M Carle     Phone: (907)266-2731
Anticipate Advertising In: January 2023
Description of Work: Apply a seal coat to the taxiway surface, select joint repairs and restripe.
Engineer's Estimate Range: Between $200,000 and $500,000
Additional Info: Surface seal taxiway

CHENA RIDGE ROAD AND CHENA PUMP ROAD RESURFACING
Federal# / IRIS Program#: 0645015 / NFHWY00570
Region: Northern Region
Location: Fairbanks North Star Borough
Manager: John J Netardus     Phone: (907)451-5448
Anticipate Advertising In: January 2023
Description of Work: Resurface Chena Ridge Road and Chena Pump Road. Project will include bridge work, drainage improvements, embankment stabilization, and roadside hardware.
Engineer's Estimate Range:
Additional Info:

CRAIG ADA IMPROVEMENTS
Federal# / IRIS Program#: 0003274 / SFHWY00377
Region: Southcoast Region
Location: Craig
Manager: Bran P Pollard     Phone: (907)465-4526
Anticipate Advertising In: January 2023
Description of Work: ADA Improvements to Craig segments 1 & 2 of the Southcoast ADA Audit. Approximately 1.8 miles of Water st./Craig/Klawock Hwy between Third Street and Craig High School. Scope of work to include sidewalk, curb ramp, driveway and street crossing improvements consistent with findings in the 2017 Southcoast ADA Audit.
Engineer's Estimate Range:
Additional Info:

Richardson Highway MP 35-40 Resurfacing
Federal# / IRIS Program#: 0711074 / NFHWY00133
Region: Northern Region
Location: Valdez
Manager: Colleen M Ackiss     Phone: None
Anticipate Advertising In: January 2023
Description of Work: Resurface the Richardson Highway between MP 35-40. Improvements include rehabilitating four embankment retaining walls bridge work, roadside hardware, drainage, and utility relocations.
Engineer's Estimate Range: Between $10,000,000 and $20,000,000
Additional Info:

SEWARD HWY: MP 0 TO 8 PAVEMENT PRESERVATION
Federal# / IRIS Program#: 0311034 / CFHWY00109
Region: Central Region
Location: Seward
Manager: Chris L Bentz     Phone: (907)269-0652
Anticipate Advertising In: January 2023
Description of Work: Resurface the Seward Highway from Milepoint 0-8. The project will also include, as necessary, improvements to pedestrian curb ramps, guardrail, guardrail end treatments, dig-outs, drainage repair, sign replacement, replacement striping, and utility adjustments as needed.
Engineer's Estimate Range: Between $10,000,000 and $20,000,000
Additional Info: Resurface the Seward Highway from MP 0-8. Project also includes markings, signage, pedestrian curb ramps, guardrail, guardrail end sections, brush clearing, drainage improvements, and utility adjustments.

SIT HALIBUT POINT RD & PETERSON AVE INTERSECTION SAFETY IMPR
Federal# / IRIS Program#: 0003214 / SFHWY00103
Region: Southcoast Region
Location: Sitka
Manager: Nathan A Purves     Phone: (907)465-4521
Anticipate Advertising In: January 2023
Description of Work: Provide additional illumination at the Halibut Point Road/Peterson Avenue Intersection to achieve a level of luminance that meets current DOT&PF standards. Modify adjacent roadway lighting as needed to maintain satisfactory continuous illumination. Establish a pass-through crossing to facilitate less challenging pedestrian movements. Improve intersection sight distance by removing utility equipment located in the southeast quadrant of the intersection, acquiring property to remove parking spaces that, when occupied, create sight line obstructions, and modifying access to an apartment building adjacent to the intersection (shorten curb cut). Replace existing S1-1 School signs with W11-2 advance pedestrian warning signs.
Engineer's Estimate Range: Between $1,000,000 and $2,500,000
Additional Info:

ALASKA HWY PASSING LANES
Federal# / IRIS Program#: 0002332 / Z606320000
Region: Northern Region
Location: Tok
Manager: Jennifer J Wright     Phone: (907)371-8949
Anticipate Advertising In: February 2023
Description of Work: Construct passing lanes at various locations on the Alaska Highway between Delta Junction and the Canadian Border. Improvements will include roadside hardware and drainage improvements.
Engineer's Estimate Range: Between $10,000,000 and $20,000,000
Additional Info:

ANC TAXIWAY Z IMPROVEMENTS EAST
Federal# / IRIS Program#: N/A / CFAPT00835
Region: Central Region
Location: Anchorage
Manager: Philip W Cheasebro     Phone: (907)269-0606
Anticipate Advertising In: February 2023
Description of Work: Extend the southern parallel taxiway from Taxiway F to Taxiway C, reconstruct the Taxiway C interlink, reconstruct Kulis Taxiway, and tie into the Kulis Apron.
Engineer's Estimate Range:
Additional Info:

ELLIOTT HWY MP 51-63 REHABILITATION
Federal# / IRIS Program#: 0651032 / NFHWY00420
Region: Northern Region
Location: Livengood
Manager: David K Fischer     Phone: (907)451-5357
Anticipate Advertising In: February 2023
Description of Work: Rehabilitate the Elliott Highway from MP 51-63 including bridge work (Tolovana River Bridge #0440), roadside hardware, drainage improvements, and utilities.
Engineer's Estimate Range: Between $20,000,000 and $30,000,000
Additional Info:

FAIRVIEW LOOP PATHWAY AND SAFETY IMPROVEMENTS (GF/GO)
Federal# / IRIS Program#: N/A / Z560200000
Region: Central Region
Location: Wasilla
Manager: Sean M Baski     Phone: (907)269-0566
Anticipate Advertising In: February 2023
Description of Work: Revised scope 3/14: This project will construct a separated pathway along Fairview Loop Road from Top of the World Circle to Edlund Road. Construction of the pathway may be extended further east depending on the available funding. Safety improvements at selected intersections and drainage improvements not included the Fairview Loop Pavement Preservation project will also be included in the project.
Engineer's Estimate Range: Between $10,000,000 and $20,000,000
Additional Info:

FAST AREA SURFACE UPGRADES FFY2023
Federal# / IRIS Program#: N/A / NFHWY00633
Region: Northern Region
Location: Fairbanks North Star Borough
Manager: John J Netardus     Phone: (907)451-5448
Anticipate Advertising In: February 2023
Description of Work: Resurface pavement, replace pavement markings, replace sidewalk curb with Americans with Disabilities Act (ADA) compliant curb ramps at street corners, improve sidewalks and pedestrian facilities, improve intersections, and install cross culverts on various streets and sidewalks in Fairbanks and North Pole.
Engineer's Estimate Range:
Additional Info:

KENAI SPUR RD REHAB: SPORTS LAKE RD TO SWIRES RD PH 2
Federal# / IRIS Program#: 0221019 / CFHWY00253
Region: Central Region
Location: Kenai
Manager: Alex L Read     Phone: (907)269-0641
Anticipate Advertising In: February 2023
Description of Work: This project will rehabilitate the Kenai Spur Highway between Soldotna and Kenai. A 5-lane highway will be constructed between the Sports Lake Road and Robin Drive intersections to increase capacity and improve safety. This is the second of two phases to construct the project.
Engineer's Estimate Range: Between $20,000,000 and $30,000,000
Additional Info:

SEWARD HWY: O'MALLEY TO DIMOND RECONSTRUCTION
Federal# / IRIS Program#: 0537008 / CFHWY00012
Region: Central Region
Location: Anchorage
Manager: Sean M Baski     Phone: (907)269-0566
Anticipate Advertising In: February 2023
Description of Work: This federally funded project will reconstruct the Seward Highway between O'Malley Road and Dimond Blvd. Work may include: new north and south bound lanes and auxiliary lanes, a new interchange connecting 92nd Avenue to Academy Drive, reconstruction of the existing interchanges within the project limits, construction and reconstruction of frontage roads, pathway and sidewalk improvements, noise walls and drainage improvements.
Engineer's Estimate Range: Between $90,000,000 and $100,000,000
Additional Info:

Seward Meridian Parkway Road Improvements, Phase II Palmer-Wasilla Highway to Seldon Road
Federal# / IRIS Program#: 0001417 / Z512210000
Region: Central Region
Location: Wasilla
Manager: Chris L Bentz     Phone: (907)269-0652
Anticipate Advertising In: February 2023
Description of Work: Upgrade Seward Meridian to a four-lane roadway and a multi-use, separated pathway along the west side from the Palmer-Wasilla Highway to Bogard Road and extend SMP one mile from Bogard Road to Seldon Road. Intersection improvements include a new roundabout at the Bogard Road intersection and a new signal at Seldon Road. A new bridge, Cottonwood Creek Bridge #1696, would replace the existing culvert at the Cottonwood Creek crossing.
Engineer's Estimate Range: Between $40,000,000 and $50,000,000
Additional Info:

TAKOTNA RIVER BRIDGE REPLACEMENT
Federal# / IRIS Program#: 0001569 / CFHWY00129
Region: Central Region
Location: Takotna
Manager: Steven J Rzepka     Phone: (907)269-0592
Anticipate Advertising In: February 2023
Description of Work: Reconstruction (replacement) of the Takotna River Bridge (bridge #0463). Reconstruction may include bridge work, roadside hardware, drainage improvements, and utilities.
Engineer's Estimate Range: Between $5,000,000 and $10,000,000
Additional Info: Replacement of the Takotna River Bridge (bridge #0463). May include bridge work, roadside hardware, drainage improvements, and utilities. Project will advertise with Z516210000 Takotna: Gold Creek Bridge & Tatalina Bridge Replacement.

TAKOTNA: GOLD CR BRIDGE & TATALINA BRIDGE REPLACEMENT
Federal# / IRIS Program#: 000S783 / Z516210000
Region: Central Region
Location: Takotna
Manager: Steven J Rzepka     Phone: (907)269-0592
Anticipate Advertising In: February 2023
Description of Work: The Alaska Department of Transportation and Public Facilities (DOT&PF) in cooperation with the Federal Highway Administration (FHWA) proposes to replace Gold Creek Bridge with a large diameter culvert, and replace the Tatalina River Bridge #462.
Engineer's Estimate Range: Between $2,500,000 and $5,000,000
Additional Info: Replace Gold Creek Bridge with a large diameter culvert, and replace the Tatalina River Bridge. Will advertise with CFHWY00129 Takotna River Bridge Replacement.

WRG GATES AND SECURITY UPGRADES
Federal# / IRIS Program#: N/A / SFAPT00412
Region: Southcoast Region
Location: Wrangell
Manager: David B Epstein     Phone: (907)465-4483
Anticipate Advertising In: February 2023
Description of Work: (1) Replace the electric vehicle gates, Gate #3 and Gate #9. Install up-to-date security systems on vehicle gates, Gate #3 and Gate #9; and (2) Install compatible/compliant security entry systems on pedestrian gates, Gate #4, #8, #11 and #13.
Engineer's Estimate Range: Between $1,000,000 and $2,500,000
Additional Info:

AMATS: EAGLE RIVER LOOP RD - EAGLE RIVER RD TO OLD GLENN HWY
Federal# / IRIS Program#: 0001694 / CFHWY00731
Region: Central Region
Location: Eagle River
Manager: Julia R Hanson     Phone: (907)269-0753
Anticipate Advertising In: March 2023
Description of Work: Pavement preservation, which may include improvements to roadside hardware, drainage, intersections, automated traffic recorders, pedestrian facilities, striping, signs, and utilities.
Engineer's Estimate Range: Between $2,500,000 and $5,000,000
Additional Info:

ANC TERMINAL WATER MAIN IMPROVEMENTS
Federal# / IRIS Program#: N/A / CSAPT00719
Region: Central Region
Location: Anchorage
Manager: Matthew H Hansen     Phone: (907)269-0602
Anticipate Advertising In: March 2023
Description of Work: Repair the water main pipes at the South Terminal, North Terminal and Old Field Maintenance.
Engineer's Estimate Range: Between $5,000,000 and $10,000,000
Additional Info:

BUCKLAND AIRPORT IMPROVEMENTS
Federal# / IRIS Program#: N/A / NFAPT00604
Region: Northern Region
Location: Buckland
Manager: Jonathan J Hutchinson     Phone: (907)451-5479
Anticipate Advertising In: March 2023
Description of Work: Rehabilitate the runway and taxiway, stabilize the embankments, resurface the airport access road, apply dust palliative, and replace the airport lighting system.
Engineer's Estimate Range: Between $5,000,000 and $10,000,000
Additional Info:

KDK REZANOFF DR RESURFACE: W.MARINE WAY TO AIRPORT
Federal# / IRIS Program#: 0003247 / SFHWY00260
Region: Southcoast Region
Location: Kodiak
Manager: Bran P Pollard     Phone: (907)465-4526
Anticipate Advertising In: March 2023
Description of Work: Resurface Rezanoff Drive from Marine Way to the airport. Associated preventative maintenance activities may include minor structural section improvements, drainage repairs, lighting and signals, striping, signs, and ADA improvements. Project Location and Length: Rezanoff Drive from Marine Way to the airport for an approximate length of 4.70 miles.
Engineer's Estimate Range:
Additional Info: (Design by Northern Region)

KDK: ADQ AIRPORT APRON AND TWY C, D AND F REHAB
Federal# / IRIS Program#: N/A / SFAPT00227
Region: Southcoast Region
Location: Kodiak
Manager: David A Pyeatt     Phone: (907)465-4490
Anticipate Advertising In: March 2023
Description of Work: ADQ airport ARFF Access improvements and Rehabilitation of Taxiway C, D and F. Project includes the non-private portion of the Apron.
Engineer's Estimate Range: Between $50,000,000 and $60,000,000
Additional Info: PFAS Investigation may cause delay depending on results and how to manage waste material

KNIK GOOSE BAY RD RECONST, VINE TO SETTLER'S BAY (GF)
Federal# / IRIS Program#: N/A / Z517170000
Region: Central Region
Location: Wasilla
Manager: Tom J Schmid     Phone: (907)269-0543
Anticipate Advertising In: March 2023
Description of Work: Reconstruct Knik-Goose Bay Rd from its intersection with the Palmer-Wasilla Hwy (MP 0.740) to its intersection with Settlers Bay Drive (MP 8.090). Work may include widening the roadway to add additional thru traffic lanes, turning lanes, as well as new signals and associated drainage and safety improvements.
Engineer's Estimate Range: Between $20,000,000 and $30,000,000
Additional Info: Project will be constructed in two phases. The first phase of construction (Fairview Loop Road to Centaur Ave., approx. 4mi) will be advertised under project CFHWY00599. This project will be part of the 2nd phase (Settlers Bay to Fairview Loop Road, approx. 4mi) will be constructed with project Z524640000.

KNIK-GOOSE BAY RD RECONST, PHASE 2
Federal# / IRIS Program#: 0525016 / Z524640000
Region: Central Region
Location: Wasilla
Manager: Tom J Schmid     Phone: (907)269-0543
Anticipate Advertising In: March 2023
Description of Work: Project will improve capacity of this segment of Knik-Goose Bay Road, likely requiring additional lanes. Includes constructing bike/pedestrian facilities and implementing appropriate safety engineering strategies and access management.
Engineer's Estimate Range: Between $20,000,000 and $30,000,000
Additional Info: Project will be constructed in two phases. The first phase of construction (Fairview Loop Road to Centaur Ave., approx. 4mi) will be advertised under project CFHWY00599. The 2nd phase (Settlers Bay to Fairview Loop Road, approx. 4mi) will be constructed under project Z524640000 and project 51717.

Manley Airport Improvement
Federal# / IRIS Program#: 3-02-0170-XXXX / NFAPT00363
Region: Northern Region
Location: Manley
Manager: Jonathan J Hutchinson     Phone: (907)451-5479
Anticipate Advertising In: March 2023
Description of Work: Construct a new apron and taxiway, install taxiway lighting, address apron electrical issues, and apply dust palliative to airport operational surfaces.
Engineer's Estimate Range: Between $2,500,000 and $5,000,000
Additional Info: Shelf Ready in 22

MEKORYUK AIRPORT SNOW REMOVAL EQUIPMENT BUILDING
Federal# / IRIS Program#: AIP 3-02-0176-003-2022 / CFAPT00269
Region: Central Region
Location: Mekoryuk
Manager: Matthew R Epp     Phone: (907)764-4881
Anticipate Advertising In: March 2023
Description of Work: Project will construct a new heated 2-bay SREB, vehicle fueling station..
Engineer's Estimate Range: Between $1,000,000 and $2,500,000
Additional Info: Pre PS&E review documents are located at the link: Preliminary Plans (~20 Mb)

PARKS HWY MP 99 - 163 DRAINAGE & CULVERT IMPROVEMENTS
Federal# / IRIS Program#: 0A41042 / CFHWY00592
Region: Central Region
Location: Matanuska-Susitna Borough
Manager: Tom J Schmid     Phone: (907)269-0543
Anticipate Advertising In: March 2023
Description of Work: Project will construct improvements to drainage including culvert repair, replacement, and new installations, as necessary to provide adequate drainage.
Engineer's Estimate Range: Between $5,000,000 and $10,000,000
Additional Info:

SEWARD AIRPORT IMPROVEMENTS
Federal# / IRIS Program#: N/A / Z548570000
Region: Central Region
Location: Seward
Manager: Joy A Vaughn     Phone: (907)269-0812
Anticipate Advertising In: March 2023
Description of Work: Shift, raise and reconstruct R/W 16/34. Construct Armor protection. Rehabilitate aprons, replace airport lighting, and construct pads for NAVAIDS. Close R/W 13/31, Taxiways A, D, and E. Miscellaneous fencing, signing, etc...
Engineer's Estimate Range: Between $20,000,000 and $30,000,000
Additional Info:

AMATS: 4TH AVE SIGNAL & LIGHTING UPGRADE
Federal# / IRIS Program#: 0001657 / CFHWY00555
Region: Central Region
Location: Anchorage
Manager: Julia R Hanson     Phone: (907)269-0753
Anticipate Advertising In: April 2023
Description of Work: This AMATS funded project will reconstructed the traffic signal and street lighting system on 4th Ave between A Street and Ingra Street. Work may included signing, Striping, ATRs, drainage, paving, pedestrian & ADA amenities, utility relocation, landscaping and roadside hardware.
Engineer's Estimate Range:
Additional Info:

ANG AIRPORT INITIATION - CLEARING
Federal# / IRIS Program#: N/A / SFAPT00086-C
Region: Southcoast Region
Location: Angoon
Manager: David B Epstein     Phone: (907)465-4483
Anticipate Advertising In: April 2023
Description of Work: Construction of a new airport and access roadways located 2.5 miles south of Angoon. CC: 24300114 LC: 33002332
Engineer's Estimate Range: Between $50,000,000 and $60,000,000
Additional Info:

GLENN HIGHWAY MILEPOST 66.5 TO 92 PAVEMENT PRESERVATION
Federal# / IRIS Program#: 0A15039 / CFHWY00394
Region: Central Region
Location: Statewide
Manager: Kristina H Busch     Phone: (907)269-0567
Anticipate Advertising In: April 2023
Description of Work: Resurface the Glenn Highway from Kings River bridge to Cascade. Additional improvements may include bridge work, roadside hardware, drainage improvements, intersection improvements, ADA improvements, and utilities as necessary. Project construction may be phased.
Engineer's Estimate Range: Between $10,000,000 and $20,000,000
Additional Info:

HSIP: 5TH AVE: CONCRETE ST TO KARLUK ST PEDESTRIAN IMPROVMNT
Federal# / IRIS Program#: 0421102 / CFHWY00856
Region: Central Region
Location: Anchorage
Manager: Christopher L Post     Phone: (907)269-7885
Anticipate Advertising In: April 2023
Description of Work: This HSIP project will construct a median barrier on 5th Avenue between Concrete Street and the couplet of 5th and 6th Avenues (Karluk Street). Work may include roadside hardware, drainage, improvements, and utilities.
Engineer's Estimate Range:
Additional Info:

JNU BRIDGET COVE CREEK CULVERT REPLACEMENT
Federal# / IRIS Program#: 0003267 / SFHWY00359
Region: Southcoast Region
Location: Juneau
Manager: Darryl Lester     Phone: (907)465-4421
Anticipate Advertising In: April 2023
Description of Work: Replace the twin culverts at Bridget Cove Creek.
Engineer's Estimate Range: Between $500,000 and $1,000,000
Additional Info: