Skip to content

Parks Highway MP 99-163 Drainage & Culvert Improvements

State/Federal Project No: CFHWY00592/0A41042

Updated December 2024

What's New

Map of project area

2023 Culvert AOP Grant Applications

Project Overview

The Alaska Department of Transportation and Public Facilities, in cooperation with the Federal Highway Administration (FHWA), is developing a project to improve culverts and drainage infrastructure within the Parks Highway corridor between Milepost 99-163. Throughout the project corridor, various culverts and drainage infrastructure are exhibiting signs of deterioration including pipe corrosion, drainage channel blockage, inlet and outlet scouring, and other deficiencies. Approximately 200 culverts in the project corridor are anticipated to be evaluated and potentially improved with this project; many were installed more than 50 years ago when the Parks Highway was initially constructed. The Department is focusing on improving the culverts in the most critical condition first.

Project Phasing

The project is being developed in phases for design and construction.

Phase 1: Replace and/or improve 10 culverts that are in critical condition and pose the most risk to the highway if they fail. The culverts addressed in Phase 1 are shown in purple on the adjacent figure. The design process is complete. Construction may begin in 2025.

Phase 2: Replace the existing 144-inch culvert at Railroad Creek (MP 128.5) with a bridge; it is shown in green on the adjacent figure. The design process is complete. Construction may begin in early 2025.

Phase 3: Replace 7 failing culverts, 2 of which may result in bridges. The culverts to be addressed in Phase 3 are shown in yellow on the adjacent figure.

Phase 4: Replace 7 failing culverts, 3 of which may result in bridges. The culverts to be addressed in Phase 4 are shown in red on the adjacent figure.

Future Phases: In the summer of 2023, the project team ranked and prioritized roughly 70 of the remaining culverts in the project corridor. Culverts addressed in "Future Phases" will be prioritized, as they are currently in poor condition.

PROPOSED WORK MAY INCLUDE
  • Drainage improvements
  • Culvert maintenance, replacement, and new installations
  • Ditch grading
  • Digouts and associated resurfacing
  • Guardrail
  • Signage
  • Utility relocations
  • Clearing and grubbing

SIGN UP FOR ELECTRONIC PROJECT UPDATES

Enter your email below to receive project updates for the Parks Highway Milepost 99-163 Drainage and Culvert Improvements project.

 

 

logo of the Alaska Project Exchange

Use DOT&PF's Alaska Project Exchange tools to learn more about all of DOT&PF's active construction projects statewide!

  • Want to know how construction will impact road traffic? Visit 511.alaska.gov
  • Want to dig into the details about projects across the state? Visit dot.alaska.gov/construction