Homer Airport Improvements
Schedule

Project # CFAPT00491 / AIP 3-02-0122-021-2023

A chart showing the timeline for the Homer Airport Improvements project
A chart showing the timeline for the Homer Airport Improvements project.

Construction on this project began in 2023 and is expected to be complete in late 2024.

2024 construction impacts include:

  • Nightly closures from 8PM to 8AM April 1 to October 31
  • FULL RUNWAY CLOSURE from 8PM Monday, April 15 to 8AM Sunday, April 21
  • South half-width runway (50ft) operations start Sunday, April 21 at 8AM
  • FULL RUNWAY CLOSURE from 8PM Monday, July 22 to 8AM Wednesday, July 24
  • North half-width runway (50ft) operations start Wednesday, July 24
  • THREE-DAY (72 HOUR) FULL RUNWAY CLOSURE from 8PM Monday, October 21 to 8AM Friday, October 25

For construction updates, call 907-242-4889. Members of the public can also join our weekly phone meetings on Thursdays at 8 a.m. with conference number 907-268-6372 and meeting ID 490419.

logo of the Alaska Project Exchange

Use DOT&PF's Alaska Project Exchange tools to learn more about all of DOT&PF's active construction projects statewide!

  • Want to know how construction will impact road traffic? Visit 511.alaska.gov
  • Want to dig into the details about projects across the state? Visit dot.alaska.gov/construction