- Public Open House (August 20, 2019 in Anchor Point)
- Bridge Alternative Selection (October 2019)
- Environmental Document Completion (May 2020)
- Design Completion (September 2020)
- Construction:
- Winter 2020 - Vegetation Clearing & Utility Relocations
- Summer 2021 - Bridge and Roadway Construction
- Spring 2022 - Remove Existing Bridge & Install Campground Kiosks