The Alaska Department of Transportation & Public Facilities (DOT&PF), in cooperation with the Alaskan Region of the Federal Aviation Administration (FAA), is proposing to rehabilitate the Haines Airport. Proposed work may include:

  • Rehabilitate Runway (RW) 08/26
  • Rehabilitate Taxiways (TW) A, D, E, and portions of TWs C and B
  • Construct a taxilane between the edge of the general aviation apron and helipad
  • Reconstruct helipad
  • Improve drainage including modifications to existing culverts and ditching
  • Replace edge lighting, airfield direction signage, conduits, and electrical conductors
  • Replace and relocate the airport rotating beacon
  • Construct a snow removal equipment building (SREB)

The purpose of the project is to extend the service life of the Haines Airport, improve safety for aircraft operations and taxiing, improve airport access, and improve drainage.

The project team is currently working on design and environmental analysis. The anticipated environmental impacts for this project have been reduced. The proposed SREB site has been relocated to avoid impacts to wetlands and water bodies. As a result of the reduced impacts, the class of action has been downgraded from an Environmental Assessment to a Categorical Exclusion for the FAA’s compliance with the National Environmental Policy Act (NEPA).


Email Updates
Enter your email address below to receive project updates directly:


logo of the Alaska Project Exchange

Use DOT&PF's Alaska Project Exchange tools to learn more about all of DOT&PF's active construction projects statewide!

  • Want to know how construction will impact road traffic? Visit 511.alaska.gov
  • Want to dig into the details about projects across the state? Visit dot.alaska.gov/construction