Skip to content

Phase 1 Federal Project No. 0221(018) | Phase 2 Federal Project No. CFHWY00253 | Phase 2 Federal Project No. 0221(019)

Kenai Spur Highway Rehabilitation Project:
Sports Lake Road to Swires Road

Update Wednesday, August 19, 2026

We began on August 17th, to install Street Lighting work from Delta Avenue to Dolly Varden a span of 7.5 miles and on both sides of the highway, installing conduit, jboxes and pile driving lighting foundations. This work will continue until the end of October.

Our contractor is working 6 days a week from 7am to 7pm. The plan is to widen the entire roadway from Robin to Silver Salmon and pave the first layer of asphalt (ATB). This work will continue to the end of September.

We then plan to excavate along the bike path near station 217+00 for the remainder of October, there is a deep dig here and will take some time.  One lane flagging operations will continue. Shifts in traffic with devices will also occur to make room for dump trucks to import gravel and widen the road. The pathway will be closed during the day to complete the road widening as heavy equipment will be traversing this section; the pathway will be reestablished at the end of shift on gravel and delineated by traffic devices.

Please drive safe this summer and enjoy the road improvements.

Update Thursday, July 23, 2026

Update Monday, June 29, 2026

Update Monday, June 1, 2026

Update Wednesday, May 13, 2026

Update April 29, 2026

Update March 27, 2026

About the project

The Alaska Department of Transportation and Public Facilities (DOT&PF) plans to rehabilitate and improve the safety of the 5.7-mile segment of the Kenai Spur Highway located between Soldotna and Kenai, Alaska.

Kenai Spur Highway project area map

The Kenai Spur Highway serves as a critical link between the communities of Kenai and Soldotna. Situated between two five-lane segments, a 5.7-mile segment of the highway from Milepost (MP) 2.4 to 8.1 bottlenecks to two lanes. This part of the roadway has higher crash rates than the statewide average, and also has the second-highest rate of moose collisions in Alaska, so safety improvements are needed. The project is a priority for both the Kenai Peninsula Borough and the State of Alaska. The project is funded with a combination of state and federal funding.

For this rehabilitation project, the five-lane highway design includes two 12-foot through-lanes in each direction and a continuous 14-foot, Two-Way Left-Turn Lane (TWLTL). These project improvements will match the section of Kenai Spur Highway from S. Forest Drive to Swires Road and carry the design through Sports Lake Road. The additional through-lanes will provide safe passing opportunities, reduce traffic platooning, and ease associated driver frustration. The continuous TWLTL will remove vehicles waiting for left-turn opportunities from through-lanes, lowering the risk of rear-end collisions. Continuous lighting will be installed between Delta Avenue and Dolly Varden Street to complete continuous lighting between Kenai and Soldotna.


Phase 1 – Eagle Rock Drive to Swires Road

Phase 1 was completed in summer 2020.

Phase 2 – Sports Lake Road to Eagle Rock Drive

In July and August 2020, a contractor cleared all trees, shrubs, and brush within the highway right-of-way (ROW) and certain utility easements along the road.

Phase 2 was advertised for competitive construction bids in July 2025. Construction is currently scheduled for completion by June 2028.

Join our mailing list

 

logo of the Alaska Project Exchange

Use DOT&PF's Alaska Project Exchange tools to learn more about all of DOT&PF's active construction projects statewide!

  • Want to know how construction will impact road traffic? Visit 511.alaska.gov
  • Want to dig into the details about projects across the state? Visit dot.alaska.gov/construction