SGY: State Street Pavement Rehabilitation

Project # Z680850000/0972018
Upcoming Activity

SCHEDULE

The SGY: State Street Pavement Rehabilitation project initially began in 2006, but was restarted in April 2018. The project is currently moving towards the 95% design (Plans, Specifications & Estimates), with Right-of-Way acquisition currently in process.

Plans, Specifications & Estimates Review will be submitted in April 2021 with advertisement planned for Winter 2021.