The following table shows the planned project schedule.
| Deliverable or Milestone | Deadline |
| Inventory & Issues summary | July 29, 2014 |
| Aviation demand forecast | October, 2014 |
| Requirements analysis chapter | December, 2014 |
| Alternatives | January, 2015 |
| Public Meeting | January 28, 2015, Wednesday 4 - 7 p.m. |
|
Northwest Arctic Borough Assembly Chambers, 163 Lagoon St, Kotzebue, AK Presentations at 4:30 and 5:30 p.m. |
|
| Implementation Plan | February, 2015 |
| Financial Implementation | March, 2015 |
| Draft Master Plan document | April, 2015 |
| Public meeting #2 | June 16, 2015, Tuesday 4 - 7 p.m. |
|
Northwest Arctic Borough Assembly Chambers, 163 Lagoon St, Kotzebue, AK Presentations at 4:30 and 5:30 p.m. |
|
| Airport Layout Plan | July, 2015 |
| Final Master Plan document | July, 2015 |
Page updated: 5/22/2015