The following table shows the planned project schedule.
Deliverable | Deadline |
Public involvement plan completion | January 18, 2013 |
Public Meeting #1 | February 26, 2013 |
Inventory existing conditions and issues | April 26, 2013 |
Land use assessment | May 4, 2013 |
Environmental overview | June 21, 2013 |
Summary of existing and potential issues | July 12, 2013 |
Public Meeting #2 | August 19, 2013 |
Environmental documentation report | September 27, 2013 |
Mapping | November 15, 2013 |
Draft master plan | November 15, 2013 |
Public Meeting #3 North Slope Borough Assembly Chambers |
December 4, 2013 6 to 8 p.m. |
Final master plan | December 13, 2013 |