The proposed road would have a design speed of 25 miles per hour and would include approximately 100 turnouts and 2-foot shoulders. The new road would terminate with a trail connection to USFS Road No. 75797 where a turnaround, trailhead parking, and some day-use facilities would be constructed.
The proposed road alignment was identified from data collected during engineering and environmental field surveys performed during 2014, 2015, and 2016. The project would traverse approximately 96 acres of primarily forested habitat. From initial field studies, the following would be needed:
• 288 culverts ranging in diameter from 24 inches to 120 inches.
• 10 Structural Plate Arch/ Culvert Arches for stream crossings with spans ranging from 6 feet to 30 feet.
• 2 bridges consisting of pre-engineered structures with spans of approximately 105 feet and 150 feet, respectively.
The Department began preliminary design and environmental baseline studies for the proposed route in spring 2014. Public and Agency scoping began in early March 2015 with a Public Notice issued on March 4, 2015 (Public Notices). Design and environmental efforts are nearing completion with project permitting planned to begin in early 2018.
The Public comment period ended on April 3, 2015.With consideration of public and agency comments, and engineering considerations, the department will make further refinements to the proposed design and complete the environmental documentation.
Environmental Document
Environmental field work was conducted during 2014, 2015, and 2016. The Katlian Bay Road Environmental Document has been released January 2018.
Use DOT&PF's Alaska Project Exchange tools to learn more about all of DOT&PF's active construction projects statewide!