Skip to content

Port Lions Airport

Improvement Project Z-52796-0000

 

IMG_2458

Project Time Lines
Below are timelines for project development:

Port Lions Airport Improvement Project Timeline
Task Target Completion Date
Ground Survey December 2017 (done)
Geotechnical Investigation Report Early Summer 2019
Final NEPA Document (Environmental Assessment) January 2020
Airport Final Design January 2020
Right-of-Way Acquisition January 2021
Construction 2021 / 2022
All dates may change as we move forward

 

Port Lions Airport Improvement Project Field Work Schedule  2018-2019
Task Target Completion Date
Geotech Phase I Data Collection March 2018 (done)
Fish Habitat Assessment May 2018 (done)
Hazardous Materials Assessment July 19, 2018 (done)
Wetland Delineation and Invasive Plant Species Survey July 18-24, 2018 (done)
Cultural Resources Investigation September 27, 2018 (done)
Geotechnical Phase 2 and Phase 3 Studies March / April 2019

 

 

Plane Landing

Have Questions?

Click here for project documents.

Click here to contact us.