Skip to content

Port Lions Airport

Improvement Project Z-52796-0000

 

IMG_2458

Project Time Lines
Below are timelines for project development:

 

Project Development Timeline
Task Target Completion Date
Ground Survey December 2017 (done)
Geotechnical Investigation Report Early Summer 2019
Final NEPA Document (Environmental Assessment) January 2020
Airport Final Design January 2020
Right-of-Way Acquisition May 2020
Advertise Project July 2020
Construction 2021 / 2022

 

Public Involvement Schedule - 2019
Task Target Completion Date
Agency Notice Commenting open through March 22
Public Notice Commenting open through April 21
Agency Scoping Meeting (Anchorage) March 6, 2019
Public Meeting (Port Lions) April 16, 2019
Public Hearing on Final EA Draft (Port Lions) Fall 2019 (date tbd)

 

Field Work Schedule  2018-2019
Task Target Completion Date
Geotech Phase I Data Collection March 2018 (done)
Fish Habitat Assessment May 2018 (done)
Hazardous Materials Assessment July 19, 2018 (done)
Wetland Delineation and Invasive Plant Species Survey July 18-24, 2018 (done)
Cultural Resources Investigation September 27, 2018 (done)
Geotechnical Phase 2 and Phase 3 Studies March / April 2019

All dates may change as we move forward

 

Have Questions?

Click here for project documents.

Click here to contact us.

 

Plane Landing