Skip to content

Valdez Pioneer Field Airport Master Plan Update
State Program Number NFAPT00291 / Federal Program Number 3-02-0311-020-2017

Master Plan Timeline (Subject to Change)

May 9, 2018 Project Kickoff
May 12-13, 2018 Valdez Fly-In
May 9, 2018 – June 20, 2018 Public Involvement Plan
May 15, 2018 – October 15, 2018 Conditions and Needs Assessment
June 1, 2018 – October 31, 2018 Land Use Assessment
Fall 2018 Public Open House
October 15, 2018 – December 15, 2018 Alternatives Analysis
Winter 2018/19 Public Open House
September 1, 2018 – December 31, 2018               Airport Layout Plan
December 31, 2018 Draft Master Plan
March 15, 2019 Final Master Plan