Master Plan Timeline (Subject to Change)

May 9, 2018 Project Kickoff
May 12-13, 2018 Valdez Fly-In
May 9, 2018 – June 20, 2018 Public Involvement Plan
May 15, 2018 – October 15, 2018                 Conditions and Needs Assessment
June 1, 2018 – October 31, 2018 Land Use Assessment
Fall 2018, Spring 2019 Public Involvement
Spring 2019 – Winter 2021 Alternatives Analysis
Winter 2020/2021 Public Open House
Spring 2021Airport Layout Plan
Spring 2021Draft Master Plan
Spring 2021Final Master Plan