The chart shows the timeline for the Juneau Access project.
1993 to 1994: Earliest scoping for JAI Project began
1997: Draft EIS released and public hearings and comment period.
2003: Scoping reinitiated for Supplemental Draft EIS.
2006: Federal Highway Administration (FHWA) issued a Record of Decision (ROD) for Juneau Access Improvements Project, Alternative 2B.
2006: Complaint filed against FHWA and U.S. Forest Service (USFS) in US District Court.
2009: District Court ruled Final EIS was not valid. State of Alaska filed an appeal with U.S. Court of Appeals for the Ninth District.
2011: Court of Appeals upheld District Court decision.
2011: Alaska Department of Transportation and Public Facilities (DOT&PF) and FHWA announced intent to complete a Supplemental EIS for JAI Project.
January 2012: Notice of Intent published.
February 2012: Scoping period.
Fall 2014: Draft SEIS released and public hearings and comment period.
December 2016: Governor selects No Action Alternative as State's recommended preferred alternative.
July 2018: Final SEIS/ROD released.