Anchor River Bridge Replacement

Schedule

 

  1. Public Open House (August 20, 2019 in Anchor Point)
  2. Bridge Alternative Selection (October 2019)
  3. Environmental Document Completion (February 2020)
  4. Design Completion (June 2020)
  5. Construction:
    • Fall 2020 - Vegetation Clearing & Utility Relocations
    • -- Winter Shutdown --
    • Summer 2021 - Bridge and Roadway Construction
    • Fall 2021 - Remove Existing Bridge