The chart shows the tentative implementation schedule with timing and duration of components and launch dates of the Alaska DOT&PF AASHTOWare Implementation Project.

Presentation

Preconstruction Analysis is scheduled to run October 2016 to April 2017.

Preconstruction Implementation is scheduled to run April 2017 to May 2018.

Preconstruction Module Launch is scheduled for May 2018.

Bids/Bid Express Implementation is scheduled to run April 2017 to May 2018.

Bids/Bid Express Module Launch is scheduled for May 2018.

Civil Rights & Labor Analysis (Phase 1) is scheduled to run October 2016 to April 2017.

Civil Rights & Labor Implementation (Phase 1) is scheduled to run April 2017 to May 2018.

Civil Rights & Labor Module (Phase 1) Launch is scheduled for May 2018.

Construction Analysis is scheduled to run October 2017 to October 2018.

Construction Implementation is scheduled to run October 2018 to January 2020.

Construction Module Launch is scheduled for January 2020.

Civil Rights & Labor Analysis (Phase 2) is scheduled to run October 2017 to October 2018.

Civil Rights & Labor Implementation (Phase 2) is scheduled to run October 2018 to January 2020.

Civil Rights & Labor Module (Phase 2) Launch is scheduled for January 2020.

Materials Analysis is scheduled to run October 2017 to October 2018.

Materials Implementation is scheduled to run October 2018 to January 2020.

Materials Module Launch is scheduled for January 2020.

Estimation Implementation is scheduled to run January 2020 to January 2021.

Estimation Module Launch is scheduled for January 2021.

BAMS/DSS is scheduled for 2021.